Jurisdiction scope: The golden thread and the Building Safety Regulator gateway process described in this article apply in England to higher-risk buildings under the Building Safety Act 2022 and the Building Safety Regulations 2023. Scotland and Wales are described separately below.
Before you start: Once the cavity is closed, the evidence you did not capture no longer exists. Photograph cavity barriers, fixings and junctions before each area is concealed. This is the most important practical point in this guide.
The golden thread is the continuous flow of accurate, up-to-date building information from design through construction to occupation. For higher-risk buildings in England – broadly, residential buildings of 18m or above – it is a legal requirement, and the Building Safety Regulator’s gateway process is the mechanism through which it is assembled and verified.
The gateway process applies to higher-risk buildings: broadly, residential buildings with at least two dwellings and a height of 18m or above, or at least seven storeys. For new buildings, work cannot start until Gateway 2 approval is granted; occupation cannot begin until Gateway 3 is complete.
Crucial Tip: Capture at the time. Do not reconstruct it afterwards.
| England | Scotland | Wales | |
|---|---|---|---|
| Legal instrument | Regulation 7(2), Building Regulations 2010 (as amended) | Regulation 8(3), Building (Scotland) Regulations 2004 (SSI 2022/136, in force June 2022) | Regulations 6(3) and 7(2), Building Regulations 2010 as amended by Building (Amendment) (Wales) Regulations 2025 (in force December 2025) |
| Height threshold | Above 11m (floor of highest storey) | Storey at 11m or above | Above 11m |
| Classification required | A2-s1,d0 or A1 | A2-s1,d0 or A1 | A2-s1,d0 or A1 | Metal composite ban | All buildings | All buildings | All buildings (from December 2025) | Key difference | BS 8414 desktop assessment route available in some cases | BS 8414 system test route removed for residential over 11m - component classifications must be complete | Broadly aligned with England; hostel, hotel and boarding house added to scope from December 2025 |
For relevant buildings, the external wall must use materials achieving at least A2-s1,d0. This applies to cladding panels, insulation in the external wall, and specified attachments such as balconies.
| What To Capture | When | Format |
|---|---|---|
| Product data: delivery notes, batch numbers, labels for every component | On delivery | Photographs of labels and delivery notes filed by product and date |
| Declarations of Performance | Before installation begins | Digital copies filed by product reference and date |
| Cavity barriers: position, product, installation | Before each area of cavity is closed | Photograph in position with a scale reference, date and plan location noted | Fixings and brackets: type, spacing, installation | Before panels are fixed | Photograph of each bracket type with written record of fixing centres | Junctions: window reveals, parapets, corners | As each junction is completed | Photographs before facing materials are applied | Inspection records | At time of inspection | Signed record with date, inspector name and competence note | Change control records | When any change is made | Written record of what changed, why, and compliance impact assessment |
The application must include as-built information for the complete external wall. Common causes of delay are missing cavity barrier evidence (cavities closed before photographs were taken), change control failures, missing batch records, and incomplete inspection sign-offs.
Scotland does not operate the Building Safety Regulator gateway process. Building warrants under the Building (Scotland) Act 2003 provide the equivalent building control function. The Building Safety (Scotland) Act 2022 introduced duties for building owners but did not replicate the England gateway structure.
The practical capture requirements – product data, Declarations of Performance, certification, installation photography and change records – are good practice and are expected by verifiers and building owners in Scotland regardless of the absence of a formal gateway. On residential or institutional projects above 11m in Scotland, assemble the same evidence set as a matter of course.
Wales does not currently operate the Building Safety Regulator gateway process applicable to England. The Welsh Government is developing its own building safety framework. For Wales projects, consult the Welsh building control body and GOV.WALES for the current requirements.
Dalply supplies Declarations of Performance, BBA certificates, EPDs and technical datasheets for every product in the range, in a format suitable for inclusion in the golden thread or building warrant file.
The golden thread is a continuous record of accurate building information from design through construction to occupation. For higher-risk buildings in England, it is a legal requirement under the Building Safety Act 2022, maintained by the principal accountable person throughout the building’s life.
The Building Safety Act 2022 golden thread requirement applies in England. Scotland has its own Building Safety (Scotland) Act 2022 which introduced building owner duties, but does not replicate the England gateway process. The underlying practice of comprehensive documentation is expected and advisable on all projects.
Photographs of cavity barriers in position before the cavities are closed; fixings and brackets before panels are installed; junction details before facing materials are applied. All photographs should have a date stamp and a location reference on plan. This applies as good practice on all projects in all three GB jurisdictions.
The Building Safety Regulator gateway process applies to higher-risk buildings, broadly 18m or above, in England. For buildings below this threshold, the Building Safety Act duty holder regime still requires competence and accountability. Good documentation practice applies to all projects.