Construction Products Reform: What Changes For Façade Specification

Status labels: This article distinguishes between what is in force, what is legislated but not yet commenced, and what is proposed. These are different legal statuses and are labelled accordingly throughout.

The UK construction products regulation system is being reformed. The February 2026 Construction Products Reform White Paper sets out the government’s preferred approach following the Grenfell Tower Inquiry Phase 2 report, the Hackitt review and the Morrell-Day review.

The reform programme is led by the UK Government and applies to Great Britain. Scotland, England and Wales share the same construction products regulatory framework, UK-wide secondary legislation, even though their building regulations differ.

Where the reform came from

The post-Grenfell regulatory response identified systemic failures in how construction products are manufactured, tested, marketed and specified. The Hackitt review (2018) recommended a new framework. The Morrell-Day review (2022) examined the construction products market and found widespread problems with test manipulation, misleading marketing and inadequate oversight. A Green Paper in 2024 to 2025 gathered views; the February 2026 White Paper followed.

The General Safety Requirement

[PROPOSED – regulations expected by end of 2026, implementation late 2027]

The GSR will impose a duty on manufacturers and importers to ensure all construction products are safe before they are placed on the market, regardless of whether a designated standard exists. This applies UK-wide (Great Britain).

Currently, only products covered by a designated standard must demonstrate conformity before being placed on the market. The majority carry no mandatory pre-market assessment. The GSR closes this gap, aligning the UK approach with the revised EU Construction Products Regulation.

Timeline

Milestone Status Expected
Construction Products Reform White Paper published In force as policy intent February 2026
General Safety Requirement regulations (Great Britain) Proposed - statutory instrument expected End of 2026
GSR implementation Proposed Late 2027
Single Construction Regulator Proposed - requires primary legislation Subject to parliamentary timetable
Digital product passports / national construction library Proposed Phased from 2027

Verify: Dates are government statements as at October 2026. Verify against GOV.UK before publication or relying on them in project programmes.

Duties for specifiers

[PROPOSED]

  • Specifying products with current, valid Declarations of Performance.
  • Checking the DoP covers the specific variant and configuration being used.
  • Keeping records of specification decisions and the evidence supporting them.
  • Documenting changes made at tender or during construction against the original specification.

What to do now

  • Specify products with current Declarations of Performance and independent certification where available – a good habit under any forthcoming framework.
  • Keep specification records documenting the evidence behind each product choice.
  • Watch for the GSR regulations when published.
  • For higher-risk buildings in England: ensure golden thread documentation is assembled from the start of design.

Construction Products Reform Frequently Asked Questions

What is the General Safety Requirement?

[PROPOSED] A UK-wide (Great Britain) duty requiring manufacturers and importers to ensure all construction products are safe before placing them on the market. Expected to be enacted by end of 2026 with a transition period to late 2027.

Does construction products reform apply in Scotland?

Yes. Construction products regulation in Great Britain is UK-wide secondary legislation and applies in Scotland, England and Wales. Scotland has its own building regulations (the Building (Scotland) Regulations 2004) but construction products placed on the GB market are regulated under the shared framework.

Will UK construction products align with the EU regulation?

The White Paper states an intent to align broadly with the revised EU Construction Products Regulation. The UK and EU frameworks remain separate; UKCA and CE marking are different routes and there is no automatic mutual recognition.