Important: Transitional status is determined by the building control body or verifier for the scheme, not by the designer or the supplier. Always seek written confirmation. This guide covers the transitional arrangements for England under Approved Document B. Scotland and Wales operate separate systems with different amendment histories and no direct equivalent of these AD B transitional provisions.
Approved Document B 2026 applies in England to building control applications submitted on or after 30 September 2026. If you have a scheme in flight and want to know whether the 2026 edition applies, this guide sets out the two conditions that must both be met to remain on the previous edition.
A scheme in England may continue to the previous edition if, and only if, both of the following conditions are met on or before 30 September 2026:
Both conditions must be met. Notification alone is not enough.
A rejected application does not satisfy the condition. Nor does a pre-application enquiry.
“Sufficiently progressed” is not defined numerically. Building control bodies look for evidence that construction work on the building itself has materially started, not merely that a contractor has been appointed or that site setup works such as hoarding and drainage diversion are under way. Foundation excavation or structural frame elements have generally been accepted; site setup alone has generally not.
Because the test is discretionary, seek written confirmation from the building control body for the specific scheme.
Schemes that satisfy both conditions may continue to the previous edition during a six-month window running to 31 March 2027, provided the scheme remains sufficiently progressed throughout.
A further set of amendments with a 2029 commencement date is incorporated in the same collated document. The same two-condition transitional structure applies. Schemes should confirm which provisions each set of amendments introduces and whether both sets affect the project.
Guide Only: Answer each question in order. The first No takes you to the 2026 edition.
Scotland operates under the Building (Scotland) Regulations 2004 and the Building Standards Technical Handbooks. There is no direct equivalent of these AD B transitional provisions; warrant applications are assessed against the Technical Handbooks current at the date of the application.
The April 2026 Technical Handbooks apply to warrant applications submitted on or after 6 April 2026.
Wales operates under the Building Regulations 2010 as amended by the Welsh Government. Consult the current Welsh Approved Document B and the building control body for transitional questions on Wales projects.
Only in England, and only if both conditions are met: notification was given and the scheme was sufficiently progressed before 30 September 2026. Scotland and Wales are governed by separate regulations.
“Sufficiently progressed” is not defined numerically. Building control bodies apply a judgement based on whether construction work on the building has materially started. Site setup alone is not sufficient. Seek written confirmation from the building control body for the specific scheme.
No. Notification satisfies the first condition but the scheme must also have started and be sufficiently progressed.
Six months from 30 September 2026 to 31 March 2027, provided the scheme remains sufficiently progressed throughout.