Approved Document B Transitional Arrangements: Which Projects Can Still Use The Previous Edition

Important: Transitional status is determined by the building control body or verifier for the scheme, not by the designer or the supplier. Always seek written confirmation. This guide covers the transitional arrangements for England under Approved Document B. Scotland and Wales operate separate systems with different amendment histories and no direct equivalent of these AD B transitional provisions.

Approved Document B 2026 applies in England to building control applications submitted on or after 30 September 2026. If you have a scheme in flight and want to know whether the 2026 edition applies, this guide sets out the two conditions that must both be met to remain on the previous edition.

The two conditions

A scheme in England may continue to the previous edition if, and only if, both of the following conditions are met on or before 30 September 2026:

  1. A building control application has been submitted, an initial notice accepted, or a building notice given.
  2. Work has started and is sufficiently progressed.

 

Both conditions must be met. Notification alone is not enough.

Condition one: notification

  • A full plans application deposited with a registered building control approver or local authority, with the plans accepted or the fee paid.
  • An initial notice given to the local authority and not rejected.
  • A building notice given to the local authority.

 

A rejected application does not satisfy the condition. Nor does a pre-application enquiry.

Condition two: sufficiently progressed

“Sufficiently progressed” is not defined numerically. Building control bodies look for evidence that construction work on the building itself has materially started, not merely that a contractor has been appointed or that site setup works such as hoarding and drainage diversion are under way. Foundation excavation or structural frame elements have generally been accepted; site setup alone has generally not.

Because the test is discretionary, seek written confirmation from the building control body for the specific scheme.

The Post-30th September 2026 Window

Schemes that satisfy both conditions may continue to the previous edition during a six-month window running to 31 March 2027, provided the scheme remains sufficiently progressed throughout.

The 2029 Amendments

A further set of amendments with a 2029 commencement date is incorporated in the same collated document. The same two-condition transitional structure applies. Schemes should confirm which provisions each set of amendments introduces and whether both sets affect the project.

Does the 2026 edition apply to my scheme?

Guide Only: Answer each question in order. The first No takes you to the 2026 edition.

  1. Was a building control application, initial notice or building notice given on or before 30 September 2026?
  2. Had work physically started on the building by 30 September 2026?
  3. Was the work sufficiently progressed beyond site setup and preparatory works?
  4. Have you received written confirmation from the building control body?

Scotland and Wales

Scotland operates under the Building (Scotland) Regulations 2004 and the Building Standards Technical Handbooks. There is no direct equivalent of these AD B transitional provisions; warrant applications are assessed against the Technical Handbooks current at the date of the application.
The April 2026 Technical Handbooks apply to warrant applications submitted on or after 6 April 2026.

Wales operates under the Building Regulations 2010 as amended by the Welsh Government. Consult the current Welsh Approved Document B and the building control body for transitional questions on Wales projects.

Approved Document B Frequently Asked Questions

Can I still build to the old Approved Document B after 30 September 2026?

Only in England, and only if both conditions are met: notification was given and the scheme was sufficiently progressed before 30 September 2026. Scotland and Wales are governed by separate regulations.

What does "sufficiently progressed" mean?

“Sufficiently progressed” is not defined numerically. Building control bodies apply a judgement based on whether construction work on the building has materially started. Site setup alone is not sufficient. Seek written confirmation from the building control body for the specific scheme.

Does a building notice on its own preserve the previous guidance?

No. Notification satisfies the first condition but the scheme must also have started and be sufficiently progressed.

How long do the transitional arrangements last?

Six months from 30 September 2026 to 31 March 2027, provided the scheme remains sufficiently progressed throughout.